Puducherry Municipality
Status of Applications forwarded between 01/04/2018 and 31/01/2019
(Report as on 02/02/2019)
Puducherry Municipality
| Sr. No. | Unit Name / File Number | Forwarding Date | Chief Inspector of Factories | Science & Technology (Pollution) | Town & Country Planning | Puducherry Planning Authority | Revenue - North | Revenue - South | Land Conversion Committee | Municipality / Commune | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Eden Garden Foods 20/DIC/EI/IGB-PM/18-19 |
23.05.18 | Date: Status: |
14-06-18 Cleared |
03-07-18 Cleared |
23-07-18 Cleared |
10-07-18 Cleared |
NA | NA | NA | Awaiting Clearances / Pending |
| 2 | Sri Amritam Tyres 72/DIC/EI/IGB-PM/18-19 |
19.11.18 | Date: Status: |
31-12-18 Cleared |
07-12-18 Cleared |
14-12-18 Cleared |
NA | 30-11-18 Cleared |
NA | 20-11-18 Cleared |
Awaiting Clearances / Pending |
Back To Previous Page | Page last updated date: 15-06-2026